Virtual power plant: managing synergies and conflicts between transmission system operator and distribution system operator control objectives
File(s)OAP-CIRED.2017.0829.pdf (432.17 KB)
Published version
Author(s)
Pudjianto, D
Strbac, G
Boyer, D
Type
Conference Paper
Abstract
In this study, the implementation of virtual power plant (VPP) as a means to coordinate the use of distributed resources for different control objectives by transmission system operator and distribution system operator is described. In order to illustrate the concept, a range of illustrative studies demonstrating the application of VPP concept on a real 11 kV system in Brixton will be presented, using data from the Low Carbon London project. The studies demonstrate the changes in the operating characteristics of the VPP area over a range of system operating conditions.
Date Issued
2017-10-01
Date Acceptance
2017-03-24
Citation
CIRED - Open Access Proceedings Journal, 2017, 2017 (1), pp.2049-2052
ISSN
2515-0855
Publisher
IET
Start Page
2049
End Page
2052
Journal / Book Title
CIRED - Open Access Proceedings Journal
Volume
2017
Issue
1
Sponsor
Engineering & Physical Science Research Council (E
London Power Networks PLC
National Grid Electricity Transmission Plc
Grant Number
EP/I031650/1
PO No: 4520618760
PO 3200342629/ TAO/22046
Source
CIRED 24th International Conference on Electricity Distribution
Publication Status
Published
Start Date
2017-06-12
Finish Date
2017-06-15
Coverage Spatial
Glasgow