Institutional barriers to a ‘perfect’ policy: A case study of the Senegalese Rural Electrification Plan
Author(s)
Mawhood, RK
Gross, R
Type
Journal Article
Abstract
This paper investigates the political and institutional factors that have influenced the success of the Senegalese Rural Electrification Action Plan (Plan d׳Action Sénégalais d׳Électrification Rurale, PASER). PASER is of interest because its innovative design attracted extensive offers of finance from donors and independent power providers, however it has had limited effect on electrification levels. This paper examines PASER׳s progress and problems in detail, with the aim of informing rural electrification policy internationally.
An extensive literature review was combined with 26 semi-structured stakeholder interviews, to produce a snapshot of the Plan׳s status after its first decade of operation. PASER׳s experiences are compared with other reform-based rural electrification initiatives across Sub-Saharan Africa.
PASER has faced significant institutional and political barriers, with delays arising from organisational opposition, inconsistent ministerial support, protracted consultations and the inherent challenges of implementing an innovative policy framework in a country with limited institutional capacity. The development of human and institutional capacity has been compromised by inconsistent political commitment. Such experiences mirror those of electrification initiatives across Sub-Saharan Africa. Whilst PASER׳s successes in garnering external support and fundraising are noteworthy and won praise from early reviews, in terms of delivery the Plan has failed to resolve common institutional barriers.
An extensive literature review was combined with 26 semi-structured stakeholder interviews, to produce a snapshot of the Plan׳s status after its first decade of operation. PASER׳s experiences are compared with other reform-based rural electrification initiatives across Sub-Saharan Africa.
PASER has faced significant institutional and political barriers, with delays arising from organisational opposition, inconsistent ministerial support, protracted consultations and the inherent challenges of implementing an innovative policy framework in a country with limited institutional capacity. The development of human and institutional capacity has been compromised by inconsistent political commitment. Such experiences mirror those of electrification initiatives across Sub-Saharan Africa. Whilst PASER׳s successes in garnering external support and fundraising are noteworthy and won praise from early reviews, in terms of delivery the Plan has failed to resolve common institutional barriers.
Date Issued
2014-10-01
Citation
Energy Policy, 2014, 73, pp.480-490
Start Page
480
End Page
490
Journal / Book Title
Energy Policy
Volume
73
Copyright Statement
© 2014 Elsevier Ltd. All rights reserved. NOTICE: this is the author’s version of a work that was accepted for publication in Energy jPolic. Changes resulting from the publishing process, such as peer review, editing, corrections, structural formatting, and other quality control mechanisms may not be reflected in this document. Changes may have been made to this work since it was submitted for publication. A definitive version was subsequently published in ENERGY POLICY, Vol.: 73, (2014) DOI: 10.1016/j.enpol.2014.05.047
Description
01.09.14 KB. OK to add accepted version to spiral, Elsevier says ok while mandate is not enforced.
Identifier
http://www.sciencedirect.com/science/article/pii/S0301421514003620